Hamburg Construction Firm Lupp Issues Ultimatum Regarding Elbtower Project
Hamburg construction firm Lupp issued an ultimatum to the Hamburg Senate regarding the Elbtower project. Thilo Moser, technical director of Lupp, issued the ultimatum to the Hamburg Senate. Moser stated that Lupp will remove construction equipment if a contract to regulate further construction is not reached soon. Moser indicated that if no contract is reached by early next year, Lupp will dismantle all equipment. This development follows ongoing negotiations between Lupp and the city regarding the Elbtower.
Construction Equipment Removal
Lupp began dismantling construction equipment on Thursday. The company plans to remove two cranes from the construction site. A third specialized crane will remain on site for now. This action follows the ultimatum issued by Thilo Moser to the Hamburg Senate. The construction firm is part of a consortium negotiating with the city regarding the Elbtower. The Elbtower is an unfinished skyscraper belonging to the insolvent Signa Group. The Signa Group was founded by René Benko, who has been convicted.
City Purchase Offer Details
The city intends to purchase a portion of the completed Elbtower to house a natural history museum. The city offered a fixed sum of 595 million Euro for the tower's partial areas. The city's contract proposal was unacceptable because it would prevent bank financing. Thilo Moser stated that the city's contract proposal was unacceptable because it would prevent bank financing. The city's offer of 595 million Euro for the tower's partial areas was presented to the consortium.
Project History and Mayor Response
Construction work on the Elbtower has been paused for approximately three years. Lupp previously halted work due to non-payment. Peter Tschentscher, Mayor of Hamburg, stated that the city will not be pressured by the dismantling of equipment. The Mayor of Hamburg stated that the city will not be pressured by the dismantling of equipment.
The situation involves the Elbtower, an unfinished skyscraper associated with the insolvent Signa Group. The technical director of Lupp issued the ultimatum to the Hamburg Senate. The technical director of Lupp indicated that if no contract is reached by early next year, Lupp will dismantle all equipment. The technical director of Lupp stated that Lupp will remove construction equipment if a contract to regulate further construction is not reached soon.
Glossary
- Hamburg Senate — The Hamburg Senate presented the bid under the slogan “Olympia in Hamburg. Eine Chance für alle.” The campaign argued that the Games could serve as a catalyst for sport, inclusion, infrastructure, urban development, economic momentum and international visibility.
- natural history museum — The Museum für Naturkunde (Berlin's natural history museum) exhibits natural history near Berlin Hauptbahnhof. It has the largest mounted dinosaur in the world (a Giraffatitan skeleton). A well-preserved specimen of Tyrannosaurus rex and the early bird Archaeopteryx are at display as well.
- Elbtower — The Elbtower is an unfinished skyscraper. It belongs to the insolvent Signa Group.